The Colorado Air Pollution Control Division issues general construction permits covering common oil-and-gas source types -- registering under one is faster than a source-specific construction permit, but only works if the source meets every condition the permit sets. A registrant has to meet all of them, not just most.

The permit text here is the current issuance, with cross-references resolved to the AQCC regulations and federal rules it cites.

Looking for the numbered AQCC regulations or ECMC rules? See Colorado regulations.

Subscribe to open the full regulations

The complete corpus — Colorado and federal, linked cross-references, updates included — is $10 / month or $100 / year, with 7 days free to start. Not sure yet? See a free sample answer first.

Annual

$100 / year

Best value · two months free

7 days free, then the price you picked. We ask for a card up front and charge it when the trial ends; cancel before then from your account page and you pay nothing.

APCD General Permit GP01

GP01 — Condensate Storage Tank Batteries

Issuance 6 · July 23, 2025

Applies to condensate storage tank batteries.

APCD General Permit GP02

GP02 — Natural Gas Fired Reciprocating Internal Combustion Engines (RICE)

Issuance 4 · July 23, 2025

Applies to natural-gas-fired reciprocating internal combustion engines at oil and gas operations.

APCD General Permit GP03

GP03 — Land Development Projects

Issuance 2 · January 24, 2020

Applies to land development projects.

APCD General Permit GP05

GP05 — Produced Water Storage Tank Batteries

Issuance 5 · July 23, 2025

Applies to produced water storage tank batteries.

APCD General Permit GP06

GP06 — Diesel Fuel – Fired Reciprocating Internal Combustion Engines (RICE)

Issuance 4 · July 23, 2025

Applies to diesel-fired reciprocating internal combustion engines.

APCD General Permit GP07

GP07 — Hydrocarbon Liquid Loadout

Issuance 4 · July 23, 2025

Applies to hydrocarbon liquid loadout at oil and gas operations.

APCD General Permit GP08

GP08 — Storage Tanks

Issuance 4 · July 23, 2025

Applies to oil and gas industry storage tanks (condensate, crude oil, produced water).

APCD General Permit GP09

GP09 — Well Production Facilities (attainment areas)

Issuance 3 · July 23, 2025 · closed to new registrations July 15, 2026

Applies to oil and gas well production facilities in attainment areas (closed to new registrations July 15, 2026; existing registrations remain active).

APCD General Permit GP10

GP10 — Well Production Facilities (nonattainment areas)

Issuance 4 · July 23, 2025 · closed to new registrations July 15, 2026

Applies to oil and gas well production facilities in nonattainment areas (closed to new registrations July 15, 2026; existing registrations remain active).

APCD General Permit GP11

GP11 — Routine or Predictable Gas Venting Emissions

Issuance 3 · July 23, 2025

Applies to routine or predictable gas venting emissions at oil and gas operations.

APCD General Permit GP12

GP12 — Well Production Facilities

Issuance 1 · May 28, 2026

Applies to oil and gas well production facilities (accepting registrations since July 15, 2026; replaces GP09/GP10 for new registrations).

Application forms and filing fees aren't reproduced here (we don't track fees) -- see CDPHE's General Air Permits page to register.